Do I Need Planning Permission for a House Extension in Surrey?

Do you need planning permission for an extension in Surrey? Permitted development size limits, 6m/8m prior approval, conservation areas, Green Belt and fees.

homeownersplanningsurreyrenovations

If you're planning a house extension in Surrey, you may not need to apply for planning permission.

Many extensions can be built under permitted development rights, which allow certain types of work to be carried out without a planning application. But the rules are quite specific. The size and position of the extension, previous work to the property, and whether the house is in a conservation area or another protected location can all change the answer.

The short answer: a single-storey rear extension of up to 3 metres (semi-detached or terraced) or 4 metres (detached), no more than 4 metres high, can usually be built without planning permission. Larger single-storey rear extensions of up to 6 or 8 metres need prior approval from the council. Two-storey side extensions, and most extensions in conservation areas or the Surrey Hills beyond a modest rear extension, will usually need a householder planning application, which costs £548 in 2026.

Red-brick cottages near Sutton Abinger, below the wooded slopes of the Surrey Hills National Landscape

Photo: Dr Neil Clifton, CC BY-SA 2.0, via Geograph and Wikimedia Commons.

There is also an important distinction between not needing planning permission and not needing approval at all. An extension can be permitted development and still require Building Regulations approval, and other matters such as party wall requirements may apply.

Surrey also isn't covered by one single local planning authority. The county currently has 11 borough and district planning authorities, including Woking, Guildford, Elmbridge, Mole Valley, Waverley and Reigate & Banstead.

This guide explains how the rules work and what Surrey homeowners should check before starting an extension. For the national rules in more detail, see our guide to whether you need planning permission for an extension in England. If you're still working out a budget, see our guide to house extension costs in Surrey.

Permitted development extension limits at a glance

Type of extensionPermitted development limitMain conditions
Single-storey rear, detached houseUp to 4m from the original rear wallMax 4m high; max 3m eaves within 2m of a boundary
Single-storey rear, semi-detached or terracedUp to 3m from the original rear wallMax 4m high; max 3m eaves within 2m of a boundary
Larger single-storey rear, detached houseUp to 8mPrior approval required (£249, 42 days); not on designated land
Larger single-storey rear, other housesUp to 6mPrior approval required (£249, 42 days); not on designated land
Single-storey sideUp to half the width of the original houseMax 4m high; not permitted development in conservation areas or National Landscapes
Two-storey rearUp to 3m from the original rear wallAt least 7m from the rear boundary; not on designated land
Two-storey sideNot permitted developmentPlanning permission required

Source: GOV.UK permitted development technical guidance for householders. All conditions must be met, and the limits apply to houses, not flats or maisonettes.

Plan-view diagram of permitted development limits: 4m or 3m single-storey rear extension, 8m or 6m larger rear extension with prior approval, side extension up to half the original width, and a 3m two-storey rear extension at least 7m from the rear boundary

Do I need planning permission for my extension?

The first question is whether the proposed extension falls within permitted development rights.

For houses in England, permitted development rights are set out principally in the Town and Country Planning (General Permitted Development) (England) Order 2015, as amended.

If every relevant condition is met, certain extensions can be constructed without making a planning application.

If one of the conditions is not met, you will generally need planning permission.

For most homeowners, the key questions are:

  • Is the property a house rather than a flat or maisonette?
  • How far will the extension project from the original house?
  • How high will it be?
  • Is it single-storey or two-storey?
  • Is it on the rear or side of the property?
  • Has the house already been extended?
  • Is the property in a conservation area, National Landscape or other designated area?
  • Have permitted development rights been removed by a planning condition or Article 4 Direction?

Local councils in Surrey make the same distinction. For example, Mole Valley states that extensions can often be carried out under permitted development, but specifically warns that the position can change where a property is listed, in a conservation area or Article 4 area, has been previously extended, or has had its permitted development rights removed.

How big can an extension be without planning permission?

For a typical house in England, the most common permitted development route is a single-storey rear extension.

Single-storey rear extensions

Under the standard permitted development rules, a rear extension can generally project:

  • Up to 4 metres from the original rear wall of a detached house.
  • Up to 3 metres from the original rear wall of any other house.

There are additional restrictions on height.

The extension must not exceed 4 metres in height, and where it is within 2 metres of the boundary, the maximum eaves height is 3 metres.

The extension must also satisfy requirements relating to its position, roof, materials and the amount of the garden or property already covered by buildings.

These measurements are based on the original dwellinghouse, not simply the house as it exists today.

That matters if the property has already been extended.

A house extension under scaffolding on Greenways, near Claygate in Elmbridge, Surrey

Photo: Robin Webster, CC BY-SA 2.0, via Geograph and Wikimedia Commons.

Can I build a 6m or 8m extension without planning permission?

There is another route that can allow a considerably larger single-storey rear extension.

Subject to the relevant conditions, a detached house can extend up to 8 metres beyond the original rear wall, while other houses can extend up to 6 metres.

However, this is not the same as ordinary permitted development.

The larger extension is subject to the prior approval process. The local planning authority must be notified and adjoining neighbours are given an opportunity to comment.

The council can consider specific matters including the impact on neighbouring properties.

Mole Valley, for example, confirms the 8-metre and 6-metre limits and states that the larger-home-extension procedure does not apply where permitted development rights have been removed or where the property is in a Conservation Area, National Landscape or is a listed building.

The Planning Portal provides the national guidance for the larger home extension process.

So if you're considering a 6-metre or 8-metre extension, don't assume it is simply "permitted development". It needs to go through the appropriate prior approval process.

Can I build a side extension without planning permission?

Side extensions have tighter permitted development rules.

A side extension can generally qualify as permitted development where it is:

  • Single-storey.
  • No more than 4 metres high.
  • No wider than half the width of the original house.
  • Within the other applicable permitted development conditions.

A two-storey side extension will normally require planning permission.

There are also additional restrictions for side extensions on designated land, including conservation areas and National Landscapes.

This is one reason why two properties that look very similar from the outside can have different planning options.

Do I need planning permission for a two-storey extension?

Two-storey extensions are subject to considerably tighter controls.

For a rear two-storey extension to qualify under permitted development, among other conditions it must not project more than 3 metres beyond the original rear wall and must maintain at least 7 metres between the extension and the boundary opposite the rear wall.

There are also restrictions relating to roof height, eaves, windows and the design of the extension.

Two-storey side extensions do not qualify as permitted development.

Because these projects have a greater effect on neighbouring properties, a planning application is often required.

Why does the "original house" matter?

This is one of the easiest parts of the permitted development rules to misunderstand.

The permitted development rules generally measure an extension against the original dwellinghouse.

Broadly, this means the house as it was originally built, or as it stood on 1 July 1948 if it was built before that date.

Previous extensions can therefore affect what you can build today.

For example, imagine a semi-detached house where a previous owner has already built a rear extension.

You cannot simply measure 3 metres from the current rear wall and assume you have another 3 metres of permitted development available.

The previous work needs to be considered when assessing the property's remaining permitted development rights.

This is one of the reasons checking the property's planning history before starting the design is worthwhile.

Can I extend my house in a conservation area?

Yes, but the rules are tighter.

Surrey has a large number of conservation areas, and permitted development rights are more restricted in designated areas.

The restrictions can affect the type of extension that can be built without planning permission.

For example, in a conservation area:

  • Side extensions are not permitted development.
  • Two-storey rear extensions are not permitted development.
  • The larger 6-metre/8-metre rear extension route is not available.
  • Additional restrictions apply to certain external alterations.

A standard single-storey rear extension can still potentially qualify for permitted development, but the ordinary limits and conditions still need to be satisfied.

A whitewashed cottage with a tiled roof and brick boundary wall in the Reigate Town Centre conservation area, Surrey

Photo: Ian Capper, CC BY-SA 2.0, via Geograph and Wikimedia Commons. The cottage is in the Reigate Town Centre conservation area.

The local council's conservation area designation and any associated planning documents should therefore be checked before relying on permitted development rights.

This is not merely theoretical. Surrey councils publish their own local design guidance for extensions in conservation areas and elsewhere.

Surrey's local councils have their own design guidance

When you do need planning permission, the national permitted development rules are only part of the picture.

Once a planning application is required, the relevant council will assess the proposal against its local planning policies and design guidance.

That can make a substantial difference to the design that is likely to be accepted.

For example, Guildford Borough Council has a Residential Extensions and Alterations Guide covering issues such as scale, form, materials, relationship with neighbouring properties and the character of the area. The council says the principles are relevant whether an extension requires planning permission or not.

Elmbridge Borough Council has moved to a Design Code SPD for applications submitted from 6 January 2025. Its previous Design and Character SPD included a dedicated Home Extensions companion guide, alongside character guidance for areas including Cobham, Oxshott, Esher, Weybridge, Walton and Thames Ditton.

Waverley Borough Council has a Residential Extensions SPD covering design, scale, materials and the relationship between an extension and the existing house. The council describes the SPD as a material planning consideration when relevant applications are determined.

Mole Valley District Council adopted new Design Code SPDs in 2025 for Ashtead, Bookham & Fetcham, Dorking and Leatherhead, alongside a new Design Guidance for House Extensions SPD.

Reigate & Banstead Borough Council also publishes detailed householder extension guidance covering single-storey and two-storey extensions, roof alterations, materials and windows. Its guidance specifically notes that poorly designed extensions can affect neighbours and the character of the area.

Surrey Heath Borough Council similarly advises in its Residential Design Guide that extensions should remain subordinate to the existing house, respect the character of the area and avoid unacceptable effects on neighbours. Its guidance generally favours matching roof form, materials and architectural details, and notes that flat-roofed extensions will generally be resisted.

The practical lesson is simple:

Permitted development tells you what you may be able to build without a planning application. Local planning policy becomes particularly important when you need planning permission.

What does the council actually look at?

When a house extension requires planning permission, the council is not simply checking whether it fits on the plot.

The proposal will be assessed against national planning policy, the council's local plan and relevant supplementary planning documents or design codes.

For a typical extension, important considerations include:

Impact on neighbours

Councils will consider whether an extension creates unacceptable:

  • Loss of daylight.
  • Overshadowing.
  • Loss of privacy.
  • Overlooking.
  • Overbearing effects.
  • Visual intrusion.

Woking planning decisions demonstrate how these issues can become important even where the overall principle of extending a house is acceptable. Its planning committee has considered the scale, bulk, proximity, ground levels and relationship to neighbouring properties when determining extension applications.

Scale and proportions

A good extension should generally read as an appropriate addition to the existing house rather than overwhelm it.

Surrey Heath's design guidance, for example, recommends lower ridge heights, setbacks and widths no greater than half the existing dwelling as ways of keeping an extension subordinate.

Materials

Councils will often expect materials to relate appropriately to the existing property.

This doesn't necessarily mean every extension has to be an exact copy of the original house, but a proposal that ignores the building's materials, proportions and architectural character can be harder to justify.

The street scene

An extension at the front or on a prominent corner plot can have a much greater effect on the appearance of the street than a modest rear extension.

This is why local design guidance can be particularly important for properties in established residential areas.

What if the property is in the Surrey Hills?

The Surrey Hills is a National Landscape, formerly known as an Area of Outstanding Natural Beauty.

National Landscape status brings additional planning considerations and affects the permitted development rights available to homeowners.

In particular, the larger 6-metre/8-metre rear extension route is not available in a National Landscape, and side and two-storey rear extensions are subject to the designated-land restrictions.

This does not mean that every extension in the Surrey Hills requires planning permission.

A modest single-storey rear extension may still qualify under ordinary permitted development rights if all the conditions are satisfied.

Where planning permission is required, however, the landscape setting becomes an additional consideration.

The Surrey Hills organisation also provides planning guidance and works with the relevant planning authorities on development affecting the National Landscape.

A change to watch

The Surrey Hills National Landscape boundary is also subject to a proposed variation.

Natural England has proposed extending the designated area by approximately 129km² and has submitted the proposal to the Secretary of State for a decision. Surrey's local government reorganisation is also taking place, with two new unitary councils due to replace the existing borough and district structure from 1 April 2027.

These changes do not mean that a proposed boundary or future council should be treated as though it already has legal effect.

For a planning decision today, check the current designation and the planning authority responsible for the property.

Can I extend my house in the Green Belt?

Green Belt is particularly relevant in Surrey, but it is often misunderstood.

Being in the Green Belt does not automatically mean that you cannot extend your house.

Nor does it automatically remove all permitted development rights.

Where an extension requires planning permission, however, Green Belt policy becomes relevant to the council's assessment.

The National Planning Policy Framework allows for the extension or alteration of an existing building in the Green Belt, provided the development does not result in a disproportionate increase in the size of the original building.

Whether a particular proposal is considered disproportionate depends on its circumstances and the applicable local policy.

This is another situation where the property's planning history matters.

What if my house is listed?

A listed building has additional protection.

You may need Listed Building Consent for works that affect the building's special architectural or historic interest.

This is separate from planning permission.

A project can therefore require:

  • Planning permission.
  • Listed Building Consent.
  • Building Regulations approval.

Or, depending on the circumstances, it may require some but not all of these.

If you own a listed property, speak to the relevant council's conservation officer or planning department before developing detailed proposals.

What is an Article 4 Direction?

An Article 4 Direction allows a local planning authority to remove specific permitted development rights in a defined area.

This means that work which would normally be permitted development may instead require a planning application.

The important word is specific.

An Article 4 Direction does not necessarily remove every permitted development right from every property in an area. The actual direction needs to be checked to establish what it covers.

The same applies to planning conditions attached to previous permissions. A property may have had permitted development rights restricted as part of an earlier planning decision.

How do I check the planning position for my Surrey property?

Before paying for detailed drawings or committing to construction, work through these checks.

1. Find your planning authority

Surrey currently has 11 borough and district planning authorities:

  • Elmbridge
  • Epsom & Ewell
  • Guildford
  • Mole Valley
  • Reigate & Banstead
  • Runnymede
  • Spelthorne
  • Surrey Heath
  • Tandridge
  • Waverley
  • Woking

The relevant council depends on the property's location. Surrey County Council is not normally the authority determining an ordinary house extension application.

Surrey's local government structure is scheduled to change on 1 April 2027, when East Surrey Council (covering Elmbridge, Epsom & Ewell, Mole Valley, Reigate & Banstead and Tandridge) and West Surrey Council (covering Guildford, Runnymede, Spelthorne, Surrey Heath, Waverley and Woking) will replace the existing borough and district councils.

For a project being planned now, use the current planning authority and check the council's website for the latest requirements.

2. Check the planning history

Look for previous:

  • Extensions.
  • Planning permissions.
  • Conditions restricting permitted development.
  • Lawful Development Certificates.
  • Refused applications.
  • Conservation area or listed-building information.

This can reveal restrictions that aren't obvious from looking at the property.

3. Check the property's designations

Establish whether the house is:

  • Listed.
  • In a conservation area.
  • In the Surrey Hills National Landscape.
  • In another protected area.
  • Subject to an Article 4 Direction.
  • Affected by a previous planning condition.

Your local council's planning map and property records are the best starting point.

Mole Valley, for example, specifically directs residents to its My Mole Valley system to check conservation area, listed-building status and planning history for individual properties.

4. Measure the extension against the original house

Don't measure simply from the current rear wall.

Establish the original rear wall and check:

  • Projection.
  • Overall height.
  • Eaves height.
  • Width.
  • Distance from boundaries.
  • Existing extensions and outbuildings.

5. Check the council's local design guidance

If planning permission is required, read the relevant council's extension guidance before the design is finalised.

This can save a lot of time.

The councils don't all use identical design policies, and some have detailed guidance for particular settlements or character areas.

6. Consider a Lawful Development Certificate

If you're confident the extension is permitted development, you can still apply to the council for a Lawful Development Certificate. It isn't compulsory, but it gives you formal confirmation that the work is lawful, which can be useful when you come to sell the property.

What if I need planning permission?

If the extension doesn't qualify as permitted development, you'll normally need a householder planning application.

The application will generally include drawings showing the existing and proposed property, including floor plans and elevations.

The exact information required depends on the local planning authority.

For example, Guildford currently requires existing and proposed elevations and floor plans, with key dimensions and specified drawing scales. It may also require additional information depending on the site, including biodiversity, archaeological or daylight assessments.

Woking similarly publishes a validation checklist for householder applications and warns that missing information can result in an application being declared invalid or its processing being delayed.

That is why the right approach is to check the specific council's validation requirements, rather than relying on a generic planning application checklist.

How much does planning permission cost in 2026?

The statutory fee for a standard householder planning application in England is £548 from 1 April 2026, up from £528.

A larger single-storey rear extension using the prior approval process costs £249.

ApplicationFee from 1 April 2026
Householder planning application (one house)£548
Prior approval for a larger home extension£249

Source: GOV.UK, Planning fees: annual indexation from 1 April 2026.

The planning application fee is only one part of the cost.

You may also need to pay for:

  • Architectural drawings.
  • Structural engineering.
  • Planning consultancy.
  • Surveys.
  • Heritage assessments.
  • Ecology or biodiversity information.
  • Other supporting documents required by the council.

Some of these won't be necessary for a straightforward extension. Our guide to the hidden costs of home renovation covers the fees and extras that are easy to miss when budgeting.

How long does planning permission take?

The standard target for determining a householder planning application is generally eight weeks from the point at which the application is valid.

That doesn't mean the entire planning process will take eight weeks.

Time is also needed to:

  • Prepare the drawings.
  • Gather supporting information.
  • Submit the application.
  • Resolve validation issues.
  • Allow for consultation.
  • Respond to any amendments or requests from the council.

For larger home extensions under the prior approval process, the relevant procedure has a 42-day determination period.

Woking Council, for example, currently states an eight-week target for applications and 42 days for householder prior notifications.

Do I need Building Regulations approval?

Usually, yes.

Planning permission and Building Regulations are separate.

Planning permission is concerned primarily with whether the development is acceptable in its location and design.

Building Regulations deal with the construction itself, including matters such as:

  • Foundations.
  • Structural stability.
  • Insulation.
  • Fire safety.
  • Ventilation.
  • Drainage.
  • Electrical work.
  • Energy efficiency.

So a rear extension could be permitted development from a planning perspective while still requiring Building Regulations approval.

Waverley Borough Council explicitly highlights this distinction and advises that structural changes such as extensions still require building regulations approval even where planning permission isn't needed.

What about Party Wall requirements?

Party Wall legislation is a separate issue again.

If your extension involves work to a party wall, building on or near the boundary, or certain excavation close to a neighbouring building, the Party Wall etc. Act 1996 may apply.

This is particularly relevant to terraced and semi-detached houses.

Planning permission does not replace the need to comply with the Party Wall Act where it applies.

You should establish whether the Act applies before work begins rather than waiting until construction is underway.

How Fort can help with your house extension

Getting the planning side right is only the beginning of an extension project.

Once the design is settled, you still need to find the right Contractor, agree exactly what they will build, manage changes and keep track of payments as the work progresses.

That's where Fort is designed to help.

Find and verify Contractors

Homeowners can post their extension project on Fort and connect with Contractors interested in the work.

Fort's Fortified Contractors go through a 15-point verification process covering their identity, business and suitability.

You can also bring an existing builder onto Fort, so you're not forced to find a new Contractor if you've already chosen who you want to work with. Before you appoint anyone, our guides on how to vet a builder and how to compare builder quotes are worth a read.

Keep the project documented

Your agreed scope of work, project stages, documents, communications, updates and changes can all be kept together in the project.

That gives both sides a shared record of what was agreed.

For an extension, this can be particularly useful when the original quotation changes or additional work becomes necessary.

Organise payments around project stages

Fort lets homeowners and Contractors structure payments around agreed milestones.

Funds for a milestone are secured before the relevant work begins. Once the stage has been completed, the homeowner can review the work and approve the payout.

Payments are processed through Stripe, Fort's payment provider. Fort does not itself hold customer funds.

The aim is to give homeowners greater visibility over what they are paying for while giving Contractors clearer visibility over the funds allocated to their work. Read more on how milestone payments protect homeowners.

Keep changes and disagreements on record

Building projects don't always go exactly to plan.

If the scope changes, the change can be documented and agreed rather than relying on a verbal conversation or a text message that gets buried. Our guide to variation orders explains how to handle changes properly.

If a dispute arises, the project record provides a shared history of the agreed work, stages, communications and changes.

Where appropriate, Fort can also arrange an independent professional assessment through a RICS-chartered surveyor as part of its dispute-resolution process.

Planning an extension in Surrey?

Whether you're still looking for a Contractor or already have one, Fort gives you a shared place to organise the project, agree the work and manage milestone payments.

Start a project on Fort, or see how Fort works for homeowners.

Sources and further guidance

This article provides general information about planning requirements for house extensions in Surrey. Permitted development rights and local planning policies can change, and the position depends on the specific property, its planning history, location and proposed design. Check the relevant planning authority before starting work. Thinking about going up instead of out? See our guide to loft conversion costs in Surrey, which also covers the planning rules for roof extensions.

Last reviewed: November 2026.

Frequently asked questions

Do I need planning permission for a single-storey rear extension in Surrey?
Not necessarily. A single-storey rear extension can often be built as permitted development if it meets the national limits and conditions. For a standard rear extension the limit is generally 3 metres beyond the original rear wall for a semi-detached or terraced house and 4 metres for a detached house, with a maximum height of 4 metres.
How big can an extension be without planning permission?
Under standard permitted development rules in England, a single-storey rear extension can project up to 4 metres on a detached house or 3 metres on other houses, measured from the original rear wall, and be no more than 4 metres high. A single-storey side extension can be up to half the width of the original house. Larger single-storey rear extensions of up to 8 metres (detached) or 6 metres (other houses) need prior approval from the council.
Can I build a 6-metre extension without planning permission?
Potentially. The larger home extension rules allow qualifying detached houses to extend up to 8 metres and other houses up to 6 metres. You must follow the prior approval process, which involves notifying the council and neighbours, and the route is not available in conservation areas, National Landscapes such as the Surrey Hills, or for listed buildings.
Does living in a conservation area mean I need planning permission?
No, not automatically. Some single-storey rear extensions can still qualify as permitted development, but permitted development rights are more restricted in conservation areas. Side extensions, two-storey rear extensions and the larger 6-metre/8-metre route are not permitted development there.
Does Green Belt mean I cannot extend my house?
No. Green Belt designation does not automatically prevent an extension or remove permitted development rights. If planning permission is required, Green Belt policy becomes important and the council will consider whether the extension is a disproportionate addition to the original building.
How much does a householder planning application cost in 2026?
The national fee for a householder planning application in England is £548 from 1 April 2026. Prior approval for a larger single-storey rear extension is £249. Drawings, structural engineering and any surveys the council requires are additional.
Do I need planning permission and Building Regulations approval?
They are separate systems. An extension may not need planning permission because it qualifies as permitted development, but it will generally still need Building Regulations approval for its structure, insulation, fire safety, drainage and ventilation.
How do I know which Surrey council deals with my property?
It depends on where the property is located. Surrey currently has 11 borough and district planning authorities: Elmbridge, Epsom & Ewell, Guildford, Mole Valley, Reigate & Banstead, Runnymede, Spelthorne, Surrey Heath, Tandridge, Waverley and Woking. Use the relevant council's planning map for your address rather than assuming Surrey County Council is responsible.